@@ -516,9 +516,9 @@
|
|
|
select
|
|
|
apope.PROCESSWORKSHOPID,
|
|
|
max(apope.PROCESSWORKSHOP) PROCESSWORKSHOP,
|
|
|
- sum(if(YEAR(apope.ACTUALFINISHDATE) = YEAR(CURRENT_DATE) and MONTH(apope.ACTUALFINISHDATE) = MONTH(CURRENT_DATE), -- 本月
|
|
|
+ sum(if(YEAR(arr.REPORTWORKTIME) = YEAR(CURRENT_DATE) and MONTH(arr.REPORTWORKTIME) = MONTH(CURRENT_DATE), -- 本月
|
|
|
aro.WEIGHT,null)) ACTUALPRODUCEVOLUME, -- 本月实际完成订单量
|
|
|
- sum(if(DATE(apope.ACTUALFINISHDATE) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY), -- 昨日
|
|
|
+ sum(if(DATE(arr.REPORTWORKTIME) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY), -- 昨日
|
|
|
aro.WEIGHT,null)) YACTUALPRODUCEVOLUME -- 昨日实际完成订单量
|
|
|
from
|
|
|
aps_process_operation_process_equ apope
|
|
@@ -537,8 +537,8 @@
|
|
|
and arr.CHECKSTATUS='已检验'
|
|
|
and aro.QUALIFIED='是'
|
|
|
and apoom.PLANPRODROLLNUM>0
|
|
|
- and (YEAR(apope.ACTUALFINISHDATE) = YEAR(CURRENT_DATE) and MONTH(apope.ACTUALFINISHDATE) = MONTH(CURRENT_DATE)
|
|
|
- or DATE(apope.ACTUALFINISHDATE) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY))
|
|
|
+ and (YEAR(arr.REPORTWORKTIME) = YEAR(CURRENT_DATE) and MONTH(arr.REPORTWORKTIME) = MONTH(CURRENT_DATE)
|
|
|
+ or DATE(arr.REPORTWORKTIME) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY))
|
|
|
and apro.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
apope.PROCESSWORKSHOPID
|
|
@@ -590,7 +590,7 @@
|
|
|
and abo.PRODUCTSTATUS in ('30','40','50')
|
|
|
and (apope.PLANPROCESSRALL-apope.CANCELROLL)>0
|
|
|
and apoom.PLANPRODROLLNUM>0
|
|
|
- and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apro.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -598,7 +598,7 @@
|
|
|
actual as (
|
|
|
-- 近12个月实际已完成订单
|
|
|
select
|
|
|
- DATE_FORMAT(apope.ACTUALFINISHDATE, '%Y-%m') month_year,
|
|
|
+ DATE_FORMAT(arr.REPORTWORKTIME, '%Y-%m') month_year,
|
|
|
sum(aro.WEIGHT) ACTUALPRODUCEVOLUME -- 当月实际完成订单量
|
|
|
from
|
|
|
aps_process_operation_process_equ apope
|
|
@@ -617,7 +617,7 @@
|
|
|
and arr.CHECKSTATUS='已检验'
|
|
|
and aro.QUALIFIED='是'
|
|
|
and apoom.PLANPRODROLLNUM>0
|
|
|
- and apope.ACTUALFINISHDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and arr.REPORTWORKTIME between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apro.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -657,7 +657,7 @@
|
|
|
and abo.PRODUCTSTATUS in ('30','40','50')
|
|
|
and (apope.PLANPROCESSRALL-apope.CANCELROLL)>0
|
|
|
and apoom.PLANPRODROLLNUM>0
|
|
|
- and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apro.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -665,7 +665,7 @@
|
|
|
actual as (
|
|
|
-- 近12个月实际已完成订单
|
|
|
select
|
|
|
- DATE_FORMAT(apope.ACTUALFINISHDATE, '%Y-%m') month_year,
|
|
|
+ DATE_FORMAT(arr.REPORTWORKTIME, '%Y-%m') month_year,
|
|
|
sum(aro.WEIGHT) ACTUALPRODUCEVOLUME -- 当月实际完成订单量
|
|
|
from
|
|
|
aps_process_operation_process_equ apope
|
|
@@ -684,7 +684,7 @@
|
|
|
and arr.CHECKSTATUS='已检验'
|
|
|
and aro.QUALIFIED='是'
|
|
|
and apoom.PLANPRODROLLNUM>0
|
|
|
- and apope.ACTUALFINISHDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and arr.REPORTWORKTIME between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apro.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -732,9 +732,9 @@
|
|
|
apo.TENANTID,
|
|
|
apope.PROCESSWORKSHOPID,
|
|
|
max(apope.PROCESSWORKSHOP) PROCESSWORKSHOP,
|
|
|
- sum(if(YEAR(apope.ACTUALFINISHDATE) = YEAR(CURRENT_DATE) and MONTH(apope.ACTUALFINISHDATE) = MONTH(CURRENT_DATE), -- 本月
|
|
|
+ sum(if(YEAR(arr.REPORTWORKTIME) = YEAR(CURRENT_DATE) and MONTH(arr.REPORTWORKTIME) = MONTH(CURRENT_DATE), -- 本月
|
|
|
apo.SINGLEROLLWEIGHT,null)) ACTUALPRODUCEVOLUME, -- 本月实际已加工量
|
|
|
- sum(if(DATE(apope.ACTUALFINISHDATE) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY), -- 昨日
|
|
|
+ sum(if(DATE(arr.REPORTWORKTIME) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY), -- 昨日
|
|
|
apo.SINGLEROLLWEIGHT,null)) YACTUALPRODUCEVOLUME -- 昨日实际已加工量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -745,8 +745,8 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='10' -- 铸轧
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and (YEAR(apope.ACTUALFINISHDATE) = YEAR(CURRENT_DATE) and MONTH(apope.ACTUALFINISHDATE) = MONTH(CURRENT_DATE) -- 本月
|
|
|
- or DATE(apope.ACTUALFINISHDATE) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY)) -- 昨日
|
|
|
+ and (YEAR(arr.REPORTWORKTIME) = YEAR(CURRENT_DATE) and MONTH(arr.REPORTWORKTIME) = MONTH(CURRENT_DATE) -- 本月
|
|
|
+ or DATE(arr.REPORTWORKTIME) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY)) -- 昨日
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
apope.PROCESSWORKSHOPID
|
|
@@ -794,7 +794,7 @@
|
|
|
and app.PROCESSCATEGORY='10' -- 铸轧
|
|
|
and apo.PROCESSSTATUS in ('30','40','50') -- 已发布
|
|
|
and (apope.PLANPROCESSRALL-apope.CANCELROLL)>0 -- 计划加工卷数- 已取消卷数合计
|
|
|
- and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -802,7 +802,7 @@
|
|
|
actual as (
|
|
|
-- 近12个月铸轧实际加工量
|
|
|
select
|
|
|
- DATE_FORMAT(apope.ACTUALFINISHDATE, '%Y-%m') month_year,
|
|
|
+ DATE_FORMAT(arr.REPORTWORKTIME, '%Y-%m') month_year,
|
|
|
sum(apo.SINGLEROLLWEIGHT) ACTUALPRODUCEVOLUME -- 当月实际已加工量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -813,7 +813,7 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='10' -- 铸轧
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and apope.ACTUALFINISHDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and arr.REPORTWORKTIME between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -846,7 +846,7 @@
|
|
|
and app.PROCESSCATEGORY='10' -- 铸轧
|
|
|
and apo.PROCESSSTATUS in ('30','40','50') -- 已发布
|
|
|
and (apope.PLANPROCESSRALL-apope.CANCELROLL)>0 -- 计划加工卷数- 已取消卷数合计
|
|
|
- and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -854,7 +854,7 @@
|
|
|
actual as (
|
|
|
-- 近12个月铸轧实际加工量
|
|
|
select
|
|
|
- DATE_FORMAT(apope.ACTUALFINISHDATE, '%Y-%m') month_year,
|
|
|
+ DATE_FORMAT(arr.REPORTWORKTIME, '%Y-%m') month_year,
|
|
|
sum(apo.SINGLEROLLWEIGHT) ACTUALPRODUCEVOLUME -- 当月实际已加工量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -865,7 +865,7 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='10' -- 铸轧
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and apope.ACTUALFINISHDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and arr.REPORTWORKTIME between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -913,9 +913,9 @@
|
|
|
apo.TENANTID,
|
|
|
apope.PROCESSWORKSHOPID,
|
|
|
max(apope.PROCESSWORKSHOP) PROCESSWORKSHOP,
|
|
|
- sum(if(YEAR(apope.ACTUALFINISHDATE) = YEAR(CURRENT_DATE) and MONTH(apope.ACTUALFINISHDATE) = MONTH(CURRENT_DATE), -- 本月
|
|
|
+ sum(if(YEAR(arr.REPORTWORKTIME) = YEAR(CURRENT_DATE) and MONTH(arr.REPORTWORKTIME) = MONTH(CURRENT_DATE), -- 本月
|
|
|
(LENGTH(trim( BOTH ',' FROM arr.BATCHNUMBER))-LENGTH(REPLACE(trim( BOTH ',' FROM arr.BATCHNUMBER), ',', '')) + 1) * IFNULL(arr.ACTUALROLLWEIGHT,apo.SINGLEROLLWEIGHT),null)) ACTUALPRODUCEVOLUME, -- 本月实际已加工量=报工批次号数量*实际输入单卷重
|
|
|
- sum(if(DATE(apope.ACTUALFINISHDATE) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY), -- 昨日
|
|
|
+ sum(if(DATE(arr.REPORTWORKTIME) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY), -- 昨日
|
|
|
(LENGTH(trim( BOTH ',' FROM arr.BATCHNUMBER))-LENGTH(REPLACE(trim( BOTH ',' FROM arr.BATCHNUMBER), ',', '')) + 1) * IFNULL(arr.ACTUALROLLWEIGHT,apo.SINGLEROLLWEIGHT),null)) YACTUALPRODUCEVOLUME -- 昨日实际已加工量=报工批次号数量*实际输入单卷重
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -926,8 +926,8 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='40' -- 精整
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and (YEAR(apope.ACTUALFINISHDATE) = YEAR(CURRENT_DATE) and MONTH(apope.ACTUALFINISHDATE) = MONTH(CURRENT_DATE) -- 本月
|
|
|
- or DATE(apope.ACTUALFINISHDATE) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY)) -- 昨日
|
|
|
+ and (YEAR(arr.REPORTWORKTIME) = YEAR(CURRENT_DATE) and MONTH(arr.REPORTWORKTIME) = MONTH(CURRENT_DATE) -- 本月
|
|
|
+ or DATE(arr.REPORTWORKTIME) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY)) -- 昨日
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
apope.PROCESSWORKSHOPID
|
|
@@ -975,7 +975,7 @@
|
|
|
and app.PROCESSCATEGORY='40' -- 精整
|
|
|
and apo.PROCESSSTATUS in ('30','40','50') -- 已发布
|
|
|
and (apope.PLANPROCESSRALL-apope.CANCELROLL)>0 -- 计划加工卷数- 已取消卷数合计
|
|
|
- and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -983,7 +983,7 @@
|
|
|
actual as (
|
|
|
-- 近12个月精整实际加工量
|
|
|
select
|
|
|
- DATE_FORMAT(apope.ACTUALFINISHDATE, '%Y-%m') month_year,
|
|
|
+ DATE_FORMAT(arr.REPORTWORKTIME, '%Y-%m') month_year,
|
|
|
sum((LENGTH(trim( BOTH ',' FROM arr.BATCHNUMBER))-LENGTH(REPLACE(trim( BOTH ',' FROM arr.BATCHNUMBER), ',', '')) + 1) * IFNULL(arr.ACTUALROLLWEIGHT,apo.SINGLEROLLWEIGHT)) ACTUALPRODUCEVOLUME -- 当月实际已加工量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -994,7 +994,7 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='40' -- 精整
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and apope.ACTUALFINISHDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and arr.REPORTWORKTIME between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -1027,7 +1027,7 @@
|
|
|
and app.PROCESSCATEGORY='40' -- 精整
|
|
|
and apo.PROCESSSTATUS in ('30','40','50') -- 已发布
|
|
|
and (apope.PLANPROCESSRALL-apope.CANCELROLL)>0 -- 计划加工卷数- 已取消卷数合计
|
|
|
- and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -1035,7 +1035,7 @@
|
|
|
actual as (
|
|
|
-- 近12个月精整实际加工量
|
|
|
select
|
|
|
- DATE_FORMAT(apope.ACTUALFINISHDATE, '%Y-%m') month_year,
|
|
|
+ DATE_FORMAT(arr.REPORTWORKTIME, '%Y-%m') month_year,
|
|
|
sum((LENGTH(trim( BOTH ',' FROM arr.BATCHNUMBER))-LENGTH(REPLACE(trim( BOTH ',' FROM arr.BATCHNUMBER), ',', '')) + 1) * IFNULL(arr.ACTUALROLLWEIGHT,apo.SINGLEROLLWEIGHT)) ACTUALPRODUCEVOLUME -- 当月实际已加工量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -1046,7 +1046,7 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='40' -- 精整
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and apope.ACTUALFINISHDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and arr.REPORTWORKTIME between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -1094,9 +1094,9 @@
|
|
|
apo.TENANTID,
|
|
|
apope.PROCESSWORKSHOPID,
|
|
|
max(apope.PROCESSWORKSHOP) PROCESSWORKSHOP,
|
|
|
- sum(if(YEAR(apope.ACTUALFINISHDATE) = YEAR(CURRENT_DATE) and MONTH(apope.ACTUALFINISHDATE) = MONTH(CURRENT_DATE), -- 本月
|
|
|
+ sum(if(YEAR(arr.REPORTWORKTIME) = YEAR(CURRENT_DATE) and MONTH(arr.REPORTWORKTIME) = MONTH(CURRENT_DATE), -- 本月
|
|
|
1,null)) ACTUALPRODUCEVOLUME, -- 本月实际已加工量
|
|
|
- sum(if(DATE(apope.ACTUALFINISHDATE) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY), -- 昨日
|
|
|
+ sum(if(DATE(arr.REPORTWORKTIME) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY), -- 昨日
|
|
|
1,null)) YACTUALPRODUCEVOLUME -- 昨日实际已加工量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -1107,8 +1107,8 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='20' -- 轧机
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and (YEAR(apope.ACTUALFINISHDATE) = YEAR(CURRENT_DATE) and MONTH(apope.ACTUALFINISHDATE) = MONTH(CURRENT_DATE) -- 本月
|
|
|
- or DATE(apope.ACTUALFINISHDATE) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY)) -- 昨日
|
|
|
+ and (YEAR(arr.REPORTWORKTIME) = YEAR(CURRENT_DATE) and MONTH(arr.REPORTWORKTIME) = MONTH(CURRENT_DATE) -- 本月
|
|
|
+ or DATE(arr.REPORTWORKTIME) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY)) -- 昨日
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
apope.PROCESSWORKSHOPID
|
|
@@ -1156,7 +1156,7 @@
|
|
|
and app.PROCESSCATEGORY='20' -- 轧机
|
|
|
and apo.PROCESSSTATUS in ('30','40','50') -- 已发布
|
|
|
and (apope.PLANPROCESSRALL-apope.CANCELROLL)>0 -- 计划加工卷数- 已取消卷数合计
|
|
|
- and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -1164,7 +1164,7 @@
|
|
|
actual as (
|
|
|
-- 近12个月轧机实际加工量
|
|
|
select
|
|
|
- DATE_FORMAT(apope.ACTUALFINISHDATE, '%Y-%m') month_year,
|
|
|
+ DATE_FORMAT(arr.REPORTWORKTIME, '%Y-%m') month_year,
|
|
|
count(arr.id) ACTUALPRODUCEVOLUME -- 当月实际已加工量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -1175,7 +1175,7 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='20' -- 轧机
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and apope.ACTUALFINISHDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and arr.REPORTWORKTIME between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -1209,7 +1209,7 @@
|
|
|
and app.PROCESSCATEGORY='20' -- 轧机
|
|
|
and apo.PROCESSSTATUS in ('30','40','50') -- 已发布
|
|
|
and (apope.PLANPROCESSRALL-apope.CANCELROLL)>0 -- 计划加工卷数- 已取消卷数合计
|
|
|
- and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -1217,7 +1217,7 @@
|
|
|
actual as (
|
|
|
-- 近12个月轧机实际加工量
|
|
|
select
|
|
|
- DATE_FORMAT(apope.ACTUALFINISHDATE, '%Y-%m') month_year,
|
|
|
+ DATE_FORMAT(arr.REPORTWORKTIME, '%Y-%m') month_year,
|
|
|
count(arr.id) ACTUALPRODUCEVOLUME -- 当月实际已加工量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -1228,7 +1228,7 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='20' -- 轧机
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and apope.ACTUALFINISHDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and arr.REPORTWORKTIME between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -1276,9 +1276,9 @@
|
|
|
apo.TENANTID,
|
|
|
apope.PROCESSWORKSHOPID,
|
|
|
max(apope.PROCESSWORKSHOP) PROCESSWORKSHOP,
|
|
|
- count(DISTINCT if(YEAR(apope.ACTUALFINISHDATE) = YEAR(CURRENT_DATE) and MONTH(apope.ACTUALFINISHDATE) = MONTH(CURRENT_DATE),
|
|
|
+ count(DISTINCT if(YEAR(arr.REPORTWORKTIME) = YEAR(CURRENT_DATE) and MONTH(arr.REPORTWORKTIME) = MONTH(CURRENT_DATE),
|
|
|
arr.HEATNUMBER, null)) ACTUALPRODUCEVOLUME, -- 本月实际已加工量
|
|
|
- count(DISTINCT if(DATE(apope.ACTUALFINISHDATE) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY),
|
|
|
+ count(DISTINCT if(DATE(arr.REPORTWORKTIME) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY),
|
|
|
arr.HEATNUMBER, null)) YACTUALPRODUCEVOLUME -- 昨日实际已加工量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -1289,8 +1289,8 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='30' -- 退火
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and (YEAR(apope.ACTUALFINISHDATE) = YEAR(CURRENT_DATE) and MONTH(apope.ACTUALFINISHDATE) = MONTH(CURRENT_DATE) -- 本月
|
|
|
- or DATE(apope.ACTUALFINISHDATE) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY)) -- 昨日
|
|
|
+ and (YEAR(arr.REPORTWORKTIME) = YEAR(CURRENT_DATE) and MONTH(arr.REPORTWORKTIME) = MONTH(CURRENT_DATE) -- 本月
|
|
|
+ or DATE(arr.REPORTWORKTIME) = DATE_SUB(CURRENT_DATE, INTERVAL 1 DAY)) -- 昨日
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
apope.PROCESSWORKSHOPID
|
|
@@ -1338,7 +1338,7 @@
|
|
|
and app.PROCESSCATEGORY='30' -- 退火
|
|
|
and apo.PROCESSSTATUS in ('30','40','50') -- 已发布
|
|
|
and (apope.PLANPROCESSRALL-apope.CANCELROLL)>0 -- 计划加工卷数- 已取消卷数合计
|
|
|
- and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -1346,7 +1346,7 @@
|
|
|
actual as (
|
|
|
-- 近12个月退火实际加工量
|
|
|
select
|
|
|
- DATE_FORMAT(apope.ACTUALFINISHDATE, '%Y-%m') month_year,
|
|
|
+ DATE_FORMAT(arr.REPORTWORKTIME, '%Y-%m') month_year,
|
|
|
count(DISTINCT arr.HEATNUMBER) ACTUALPRODUCEVOLUME -- 当月实际已加工量=炉次的数量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -1357,7 +1357,7 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='30' -- 退火
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and apope.ACTUALFINISHDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and arr.REPORTWORKTIME between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -1390,7 +1390,7 @@
|
|
|
and app.PROCESSCATEGORY='30' -- 退火
|
|
|
and apo.PROCESSSTATUS in ('30','40','50') -- 已发布
|
|
|
and (apope.PLANPROCESSRALL-apope.CANCELROLL)>0 -- 计划加工卷数- 已取消卷数合计
|
|
|
- and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and apope.PLANENDDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|
|
@@ -1398,7 +1398,7 @@
|
|
|
actual as (
|
|
|
-- 近12个月退火实际加工量
|
|
|
select
|
|
|
- DATE_FORMAT(apope.ACTUALFINISHDATE, '%Y-%m') month_year,
|
|
|
+ DATE_FORMAT(arr.REPORTWORKTIME, '%Y-%m') month_year,
|
|
|
count(DISTINCT arr.HEATNUMBER) ACTUALPRODUCEVOLUME -- 当月实际已加工量=炉次的数量
|
|
|
from
|
|
|
aps_report_records arr
|
|
@@ -1409,7 +1409,7 @@
|
|
|
apope.deleted='0' and apo.DELETED='0' and arr.deleted='0'
|
|
|
and app.PROCESSCATEGORY='30' -- 退火
|
|
|
and arr.REPORTWORKSTATUS='已报工'
|
|
|
- and apope.ACTUALFINISHDATE between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and CURRENT_DATE -- 近12个月计划
|
|
|
+ and arr.REPORTWORKTIME between DATE_FORMAT(DATE_SUB(CURRENT_DATE, INTERVAL 11 MONTH), '%Y-%m-01') and DATE_FORMAT(LAST_DAY(CURRENT_DATE()),'%Y-%m-%d 23:59:59') -- 近12个月计划
|
|
|
and apo.TENANTID=#{tenantId}
|
|
|
group by
|
|
|
month_year
|